Start of works – end of January 2021. Construction work was completed in June 2023. The works took place on ul. Św. Marcin from ul. Ratajczaka to Al. Marcinkowskiego and on Al. Marcinkowskiego from ul. Św. Martin to pl. Wolności – in the very centre of Poznań.
More than 500 m of tram track have been built, along with the necessary infrastructure (overhead contact line, switch control, and heating, etc.). We rebuilt the road system in conjunction with the underground infrastructure, including general sewage, water supply, gas, telecommunications, and electricity networks.
We planted low greenery and 46 trees, including 10 in concrete pots. We installed 2 bus shelters with passenger information boards, 19 benches, and 34 bike racks.