NEWS | Extension of DW 190 in the Wągrowiec District
On 18 July 2025, we concluded an agreement with the Wielkopolska Voivodeship Road Administration in Poznań for the extension of voivodeship road No. 190 in the Wągrowiec district.
The scope of work will include an 11.085 km-long road section, as well as the construction and reconstruction of 16 engineering facilities. The project will also include the reconstruction of intersections with district and municipal roads, as well as the realisation of exits, pavements, cycle paths and pedestrian and cycle routes. New bus bays and bus stops will also be built. The completion of all works is planned for 2027.
The project is co-financed by the European Union, with a total value exceeding PLN 76 million.
The work will be carried out in phases from July 2025 to the end of December 2026. A temporary traffic organisation is being put in place to ensure the safety and fluidity of traffic during the works.
Highlights:
- Traffic in the direction of Wągrowiectravels one-way on the repaired road for vehicles up to 3.5 tons.
- Traffic towards Margonin (cars up to 3.5 tons) is being diverted via local detours – diversion routes will be clearly marked at each stage of the works.
- Cars exceeding 3.5 tons must use the main detour through Wągrowiec – Gołańcz – Margonin (roads DW193, DW241, DW242); this detour will remain in operation throughout the investment.
- It is possible to temporarily close intersections and make changes in the course of detours – always pay attention to the current signage.
- Access to properties, farms and utilities and supplies remains maintained; appropriate conditions and access information will be provided at each stage.